Biratnagar ICP
Land acquisition completed. (Nepal: 110 Bigha, India = 70 Acre)
Demarcation from Budhnagar VDC to Koshi Highway has been done.
Tender is accepted from DRAI Pvt. Ltd., India on 19 Sept 2016.
Joint Inspection visit of Govt. of Nepal (Ministry of Urban Planning and Nepal Intermodal Transport Dev. Board, Customs Department, etc.) and Govt. of India happened on 2072 Chaitra 05.
Construction at Indian side has completed about 60%.
Impressions:
Nepal Side:
There are High-tension Lines and transformers at 3 places on ICP construction area and some huts are made.
Nepal Electricity Authority should clear the high tension lines and transformers at their earliest.
Master list received from Indian side should be accepted at earliest by the concerned authorities of Nepal so that the project could be completed in time.
Indian Side:
Master list will be provided very shortly.
Indian Company is saying that no work will be started till the site is cleared.